Asia’s Project Boom Puts Logistics Infrastructure to the Test


Investment Needed to Ensure Project Delivery, Panel Says in Singapore



Asia’s expanding investment in energy, manufacturing and digital infrastructure is creating major project cargo opportunities, but success will depend on whether transport networks and logistics capabilities can keep pace.

That was a key takeaway from the “Megaproject Asia: Delivering the Next Phase of Industrial Growth” panel session at Breakbulk Asia in Singapore, moderated by Dharmendra Gangrade, head of logistics management center at Larsen & Toubro.

Gangrade opened the discussion by telling the audience that roughly 30% of global investment was taking place in Asia, which he defined broadly to include West Asia, Central Asia, the Far East, Southeast Asia, Australia and New Zealand.

The opportunities span multiple regions and sectors.

Kohki Uemura, CEO of DENZAI, highlighted onshore wind projects in Vietnam and the Philippines, Vietnam’s nuclear and grid developments, and Kazakhstan and Central Asia as markets to watch over the next three to five years.

Yohan Beal, director of operations for APAC and MEA at CEVA Logistics, pointed to Papua New Guinea and Australia, where project activity is picking up, while Ben Collins, global project cargo manager at MSC, cited large capital projects in Southeast Asia and the intra-Asian markets that will be crucial for supply.

“We definitely see the Asian market (as) being very strong,” Beal said. “The current geopolitical consequences are bringing a lot of opportunities and activity to our region.”

But the panel warned that manufacturing capacity is not always matched by the infrastructure needed to handle what factories produce.

The China-plus-one strategy has helped expand production across Southeast Asia, but land transport remains a weak point in locations such as Indonesia, parts of India and more remote areas of the Philippines. Some projects have encountered factories without suitable jetties or ports with insufficient water depth.

“The capacity to produce is not the same as the capacity to deliver,” Beal said, arguing that transport engineers should be involved before fabrication locations and procurement contracts are finalized.

Planning Before the First Module Moves

Uemura said heavy cargo movements require carefully engineered transport plans and thorough infrastructure studies. He cited problems with inland transportation during large onshore wind developments in Vietnam, arguing that high-quality route surveys and experienced transport engineers were essential to avoiding delays.

The scale of the challenge is also growing.

Yvette Shi, VP of Shanghai Megamove Logistics Technology, said her company had transported a module weighing 9,000 tons this year. Ultra-large modules require specialist deck carriers, which may sail at only eight knots in favorable conditions, need shelter during voyages and depend on SPMTs for loading and discharge. Weather and tide windows can further extend delivery times.

The panel also highlighted fragmented availability of specialist equipment, including heavy-lift cranes with capacities exceeding 1,000 tons, which often need to be mobilized across borders alongside experienced personnel. Local regulations, visa requirements and a shortage of experienced engineers add further complexity.

The proposed solution was more integrated planning, bringing transport engineers, ports, shipping lines and logistics providers into discussions before designs and routes are finalized. Logistics feasibility should also become a formal consideration in procurement decisions.

Felix Schoeller, chief commercial officer at AAL Shipping, urged project stakeholders to involve shipping lines early, noting that carriers can draw on experience with alternative ports and previous cargo movements to help shape transport plans.

“We might have another idea, right? We might have another port that we’ve worked with, where we’ve shipped cargo for other clients,” he said. “Planning really is the key. Once you’ve set your route and done your transport and road planning, it’s very hard to change.”

Collins agreed, pointing to how the scope of projects — some starting two or three years in advance — quickly narrows. “The earlier we go, the better the outcome,” he said.

“It’s the strength of the relationship between the customer and the service provider at the end of the day. And the stronger that is, the better the outcome for all, and the bigger the chance of success.”

Read more: Rethinking Routes, Prioritizing Certainty

Top photo: Dharmendra Gangrade, Felix Schoeller, Kohki Uemura, Ben Collins, Yohan Beal, Yvette Shi. Credit: Hyve